•Project Cost: ₹ 0.63 Cr.
•Name of Executing Agency : JSCL
•Execution Period: 6 months.
•Project Status: Work Completed
•Project Features :
oSmart Traffic Booths are proposed to be installed at 25 Locations
oThe traffic booths will be pre-fabricated using 50 mm thick PUF panelling walls & Pre-fabricated Single unit Toilets.
oIt is also proposed to provide single unit prefabricated Toilets at locations where, there is no Public or community toilet in the near vicinity.